Factory Acceptance Test (FAT) and Site Acceptance Test (SAT)

#factory-and-site-acceptance-testing
Also called
  • FAT
  • SAT
  • Factory Witness Test
  • Site Acceptance Test

Plain-English definition

Formal quality gates verifying critical equipment before and after shipping: Factory Acceptance Testing (FAT) proves build quality, nameplates, and control logic on the manufacturer's test bed, while Site Acceptance Testing (SAT) verifies undamaged installation and field wiring on site.

Why it matters on shift

Catching a miswired current transformer or undersized heat exchanger at the factory costs days to fix on the assembly line, whereas discovering it after rigging onto a rooftop pad delays hall turnover by months.

Illustrative operational example

During an illustrative CDU factory witness test, engineers verify hydro-static pressure hold at 1.5x design working pressure, duplex pump failover timing, and Modbus register maps before authorizing shipment.

Scope, code & safety boundary

Passing FAT never waives SAT: shipping vibration loosens busbar torque, disturbs relay harnesses, and introduces construction debris requiring fresh field verification.

Related courses & interactive lab practice

BeginnerRS-102~87 min open lessons
Utility to Rack

Critical power & dual-path feeds

AdvancedRS-203~85 min open lessons
AI Density Lab

High-density AI cooling & commissioning

Free interactive simulator
Campus Shift · 6-Mission Browser Lab

Walk a 2N data center campus across six guided browser missions with no login required.